HGC Slides for April 2025 Review
- 2025 HGC Annual review: https://indico.cern.ch/event/1523635/
- Grade C installable ?
- What is the cadence after August
- A: Produciton 4x per week
Logs
18 April 2025 Friday
- Sent draft
- Risk registry
- https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=13480
- CMU HGC Current Burn Rate
- refined draft
- Make EVMS plots
16 April 2025 Wednesday
- CAM Turnaround Report
- 16 modules /day * 5 days /week * 0.03 m2 / module
- HGC Estimate to complete Spring 2025
- HGC MAC BoEs
- Manfred: where do the plots come from? (From the datasets of the CAMTools)
11 April 2025 Friday
- Wrote up MAC meeting slides MAC Meeting 9 April 2025
- Start HGC slides
- https://indico.cern.ch/event/1536369/
- Can draw a lot from: MAC Meeting 9 April 2025
Feedback
- Add outline
- How long are you off of the critical path
Here are my notes on questions people asked for your talk, in case this is useful:
milestones, production start, light on schedule, something at the beginning to talk about schedule start when, what rate and when we are done.
use P6, how many days off the CP - subproject CP plot
lack of schedule slides
In summary, say what they should take away from the talk
slide 19: why green is so low in TTU; time scale do not match and numbers do not match to get the total
When are you done, no KPP defined for this area only
doing time and motion studies
anything about rework? from CAF